What got on the list, and what didn't?

Clermont County's five-year sewer plan (map dated May 8, 2026) has 28 projects. For each one we ask: what put it there? A permit deadline, new development, a grant, old age, or a court order? And why aren't the plants and stations failing right now on it?

The short version

Project by project

"Why it's there" comes from the plan's own description where it gives one. Where it doesn't, we've asked for the records and marked it unknown.

ProjectCostWhy it's there
Middle East Fork improvements$12.55MPlan says: raise peak wet-weather treatment capacity. The plant overflowed in 2021 and 2025.
Middle East Fork expansion (2030)$20MPlan says: more capacity, and nutrient removal "to meet OEPA/NPDES Permitting." A permit requirement.
Lower East Fork improvements$25.9MUnknown. Records requested.
Lower East Fork expansion$49.3MCapacity. Who needs it? Unknown.
Newtonsville sewer and plant~$8.2MNew service, partly grant-funded.
Arrowhead plant eliminationSends its flow to Wards Corner, which was over its ammonia limit in Feb 2026.
Shepherd Rd and Viking lift stations, Hall Run sewerAll three were named in the 1989 court order. Back on the list 37 years later.

Missing

Not on the planThe record
Nine Mile Creek plantIn significant noncompliance now.
Nine Mile & SR 131 collection repair$3,107,000 budgeted in the 2025 plan. Gone from 2026. Done, dropped or moved? Unknown.
Wards Corner plantAmmonia more than double its limit in Feb 2026, and the plan sends it more flow.
Cook Road pump stationYears of odor complaints.

Approved outside the plan

Grove Park, Miami Township: a county sewer pump station was built for it in an earlier phase, and in January 2026 the county approved a revised plan for 253 lots (staff report (opens in a new tab)). Its homes pay the same sewer rate as everyone else, so if the station costs more to run and replace than they bring in, every other customer covers the difference. The county's one-time sewer capacity charge is $3,340 per home and hasn't changed since 2011.

The pattern

Projects with a written permit deadline get funded. Violations with no penalty don't. When the state doesn't enforce, the plan follows growth instead of the law. More on why.

ORC 6111.44Every one of these projects needs the Ohio EPA Director's approval, and he may stipulate modifications, conditions. He could require the failing plants be fixed first.