Wilmington voters reverse data center rezoning, about 80 to 20 (opens in a new tab)
The referendum reversed all four rezonings for a roughly 500 MW, 545-acre campus. The developer had already ended its land deal.
Everything we track in Wilmington, newest first.
The referendum reversed all four rezonings for a roughly 500 MW, 545-acre campus. The developer had already ended its land deal.
Nine buildings, about 1.9 million square feet, $4 billion. The state had already awarded its sales tax exemption.
Part of Clinton County.
| Plant | Quarters with violations | Serious violation | Over the limit for | Penalties |
|---|---|---|---|---|
| Roberts Development Commerce Park Wwtp (opens in a new tab) Wilmington · Private | 7 of 12 | No | Reporting or schedule | $0 |
| Wilmington Wwtp (opens in a new tab) Wilmington · Public | 2 of 12 | No | BOD, carbonaceous [5 day, 20 C], Solids, total suspended | $0 |
Source: U.S. EPA ECHO, pulled 2026-11-29. Matched by the plant's city on its permit.